Project Management Q&A

OK finally a free place for Free advice on Project Management, Microsoft Project & Project Planning.

Its simple really, just click COMMENT and type in your questions and I will get back to you with the answer as soonest possible. It would be nice if you can register as a member as membership has its advantages (like free samples)

Or if you are of the shy type, then send me an e-mail at drsyed88@yahoo.com, and I will publish the answer here (and e-mail you a copy too).

4 comments:

Syed Naguib, PhD said...

Ladies & Gentlemens, OK, so the page is up & running. So start asking your questions.

I would encourage you to register so as I am able to know the person" asking. Having a name is better the just Dear Annoymous

Cheers!

Yazeer said...

Dear Tok Guru,

Cucu Guru in da' net!

Is there any special registration other than the 'blogspot' registration?

Freebies are welcome (can't be greedier, heheheh...)

By the way, your fundamental course rocks!

Happy Ramadhan, Happy Iftar w Murtabak,and Eid Mubarak!

Anonymous said...

Doc, salam aidilfitri.

seek your comment on the follwg:

in ensuring the monetary appear in Msprject is EXACTLY as per submitted claim :

A. PREPARATION OF WORK PROGRAMME
1. for submission to client, whatever item without quantities or rate, put it as FIXED COST . i.e: prep report, office equipment.

2. quantities with rate (i.e: excavation, plastering etc) put it as MATERIAL QTTY x RATE. i.e: 2000m3 sand x RM20.60/m3.

3. to avoid MANPOWER/MACHINERY interuption in determining the duration, UNCHECK the EFFORT DRIVEN option.


B. TRACKING
1. try NOT to track by ENTERING percentage at %complete. %percentage should refer to somethg i.e manhour, material etc. KEY IN the material usage at RESOURCE USAGE. msproject will automatically generate the percentage value.

-le holdfast-

Yazeer said...

Doc,
May I add my thin opinion on all questions & answers?
seems that the fella is "Dear Anonymous". Hua hua hua...